top of page
Search
cpmrealtyinfo1

88 Kensington, Kensington


There is a lot of action on site at 88 Anzac Parade, with the structure construction and internal fitouts underway. We have been informed some owners have asked questions as to whether the site will be delivered in two stages. i.e. the Northern half and Southern half. The Project Manager has confirmed that this will not be the case. To explain this futher, the reason that the Northern half is currently further progressed than the Southern portion is because excavation works on the Southern corner took longer to complete. In order to not delay the construction works, Luxcon made the decision to commence building on the Northern portion rather than wait for the whole site to be excavated completely. The Southern portion of the site is progressing now quite quickly and internal fitouts have commenced in the Northern portion lower levels. Please see below a more detailed account of the works progress on site: - All basement works are now complete. - Basement 2 ground slab has been completed as has the basement 1 carpark slab which was poured last week. - The remaining Southern half of the ground slab is currently being formed and is anticipated to be poured mid-April. - The Northern half of the site has structure currently compelted up to level 7, with level 8 currently being formed up. - It is anticipated that the structure for the Northern portion of the site will be completed by mid-April. - Internal walls and services installation has commenced on level 3 on the Northern half of the site. - Tiles have been ordered for laundries and bathrooms.

24 views0 comments

Recent Posts

See All

Aster Apartments, Crows Nest

Project Update September 2018 We are happy to advise that the apartments at Aster, Crows Nest are nearly finished. At this stage, we are...

Ryde Garden, North Ryde Inspections

Please be advised that Pre-Settlement Inspection Invitation for Ryde Garden Building C has been distributed to purchasers. Inspection...

bottom of page