Mosaic, Bankstown

May 30, 2016

We are happy to advise construction works at 74-76 Kitchener Parade commenced in April 2016, following a 3 month period of design finalisation and construction planning and immediately after the approval of the construction certificate.

Project Built were awarded the contract and are running to schedule, with the current forecast completion date in quarter 3 of 2017.

The project manager has advised us that the work scheduled in the immediate future will include completion of piling, bulk excavation and the commencement of the actual structure. We are confident you will start seeing significant and continual progress moving forward.

We will be in touch in 3 months’ time and keep you informed of the progress.

 

 

 

 

Share on Facebook
Share on Twitter
Please reload

Please reload

Search By Tags
Please reload

Archive

CONTACT US

FOLLOW US

  • Grey Facebook Icon
  • Grey Instagram Icon
  • Grey LinkedIn Icon
  • Grey Pinterest Icon
  • Grey YouTube Icon

Phone:

Email: 

+61 2 9247 1299

Head Office:

Level 4,

157-161 Gloucester Street

The Rocks,  NSW  2000  Australia

© 2017 Copyright By CPM Realty

ALTERNATIVELY YOU CAN FILL

IN THE FOLLOWING CONTACT FORM: