Mosaic, Bankstown


Project Update August 2017,

We are writing to give you an update on the progress of Mosaic Apartments, Bankstown. All services in the basement have progressed and are nearing completion.

Fitout Works

The exterior facade panelling is now completed and fitout works are progressing well with internal partitions and services underway on the top floor (level 8). Finishes trades have commenced in lower levels.

Forecast Completion

At this stage we estimate the works will be completed in November 2017. We will update you again as milestones are achieved and keep you informed of the progress. If you have any questions, please call or email us.

#Mosaic #Bankstown

106 views

Recent Posts

See All

Aster Apartments, Crows Nest

Project Update September 2018 We are happy to advise that the apartments at Aster, Crows Nest are nearly finished. At this stage, we are able to book in valuers to complete your financing arrangements

Ryde Garden, North Ryde Inspections

Please be advised that Pre-Settlement Inspection Invitation for Ryde Garden Building C has been distributed to purchasers. Inspection times will be available for respective levels on different timefra

CONTACT US

Phone:

Email: 

+61 2 9247 1299

Head Office:

Level 4,

157-161 Gloucester Street

The Rocks,  NSW  2000  Australia

© 2020 Copyright By CPM Realty

FOLLOW US

  • Grey Facebook Icon
  • Grey Instagram Icon
  • Grey LinkedIn Icon
  • Grey Pinterest Icon
  • Grey YouTube Icon

ALTERNATIVELY YOU CAN FILL

IN THE FOLLOWING CONTACT FORM: