We are happy to advise that the builders are progressing well with the construction of the apartments. From passing by the site and the photos below, the builders are up to Level 3 of Building A and Level 5 of Building B. We are predicting that the internal fitout of the apartments will commence from July 2017 and the External Structure will be completed to both Buildings by September 2017. At this stage we estimate settlements taking place in mid 2018. We will update you again towards the end of the year and keep you informed of the progress.