top of page
Search
  • cpmrealtyinfo1

Ashfield Central, Ashfield


We are happy to advise that the builders are progressing well with the construction of the apartments. From passing by the site and the photos below, the builders are up to Level 3 of Building A and Level 5 of Building B. We are predicting that the internal fitout of the apartments will commence from July 2017 and the External Structure will be completed to both Buildings by September 2017. At this stage we estimate settlements taking place in mid 2018. We will update you again towards the end of the year and keep you informed of the progress.


247 views0 comments

Recent Posts

See All

Aster Apartments, Crows Nest

Project Update September 2018 We are happy to advise that the apartments at Aster, Crows Nest are nearly finished. At this stage, we are able to book in valuers to complete your financing arrangements

Ryde Garden, North Ryde Inspections

Please be advised that Pre-Settlement Inspection Invitation for Ryde Garden Building C has been distributed to purchasers. Inspection times will be available for respective levels on different timefra

bottom of page